CWLP Peaking Turbines
CWLP operates three peaking generators, two that are oil-burning and
one that has dual-fuel operating capabilities. These units have a combined
maximum capacity of 145 MW.
Together, in 2010, these peaking turbines used a total of 412,319 dekatherms of natural gas costing
$2,123,965 and 12,145 gallons of fuel oil costing $27,696 to generate
31,878 MWH of electricity. The average net fuel cost to operate these units
was $67.50 per MWH.