|
Dallman 4 Power Station
Dallman 4 earns
top 2009 plant of the year honors from
both POWER and Power Engineering magazines.
Read more. |
At 4:09 p.m., Thursday,
November 19, 2009, CWLP assumed operating control of Dallman 4—the utility's
newest electric generating station—from KBV Springfield Partnership, the
plant's general contractor. This event signaled a major step forward for
CWLP and the customer-owners it serves.
| The
Genesis of a Power Plant: Dallman 4—a pamphlet commemorating
the history of the Dallman 4 project in words and pictures—is
available free of charge while supplies last.
Order yours online. |
Dallman 4, a 200-MW pulverized coal power plant,
is one of the cleanest coal-fired generating units in the nation.
It's completion ensures the city of Springfield a cost-efficient, reliable
and environmentally responsible source of electric power for the next
several decades. Considering fuel costs alone, in 2011 Dallman 4 was 12.43%
more efficient than Dallman 3, which is the most efficient of the three older Dallman units.
Construction was begun on the plant in late 2006.
Although still in the testing phase, the plant became operational on May 11,
2009, when—under power of natural gas—it produced 13 MW of electricity as
the unit was synchronized to the grid. As testing continued, the plant began
operating using coal on June 1. Systems-testing was completed on November
19, at which time KBV handed over operating control of the plant to CWLP. In addition to being
completed months ahead of its contract completion date, Dallman 4 came in under its projected $454.6
million budget, a feat virtually unheard of in the power industry.
The new 200-MW unit, employing a
Foster Wheeler pulverized coal boiler, replaced 76 MW of old
coal-fired technology—the utility's two
Lakeside turbine generators. Lakeside Units #6 and #7, CWLP's oldest
still-operating turbine generators, were placed into service in
1961 and 1965, respectively. Although they have not yet been
formally decommissioned, the Lakeside plants are no longer being
used.Dallman 4 employs a number of environmental control
technologies, including:
|
1. |
low-NOx burners for the boiler; a
selective catalytic reduction (SCR) system for additional NOx
removal; |
|
2. |
powdered activated
carbon injection for mercury removal; |
|
3. |
a fabric filter bag
house to remove fine particulate; |
|
4. |
a wet flue gas desulfurization unit (scrubber) for the removal of SO2;
and |
|
5. |
a wet electrostatic
precipitator to remove acid mist and ultra-fine
particulate from the
flue gas. |
This equipment
assists CWLP in its goal of becoming one of the most
environmentally friendly primarily coal-fired electric utilities
in the nation.
Air emission controls aren't the only way Dallman 4
is complementing the utility's efforts to protect and preserve
the environment. By utilizing state-of-the-art cooling towers, CWLP
is able to avoid discharging high-temperature
cooling water
from the plant into Lake Springfield.
KBV Springfield Power Partners served as general
contractor for the construction project; Black & Veatch designed
the plant, while Kiewit provided the construction; and Burns &
McDonnell served as owner's engineer on behalf of CWLP.
Learn more about Dallman 4. |
|
Dallman 4 Fun
Facts |
|
1. |
The
unit will burn 700,000 tons (1.4 billion pounds) of
Illinois coal each year. |
|
2. |
The
demand for coal will support 80 new mining jobs in Illinois. |
|
3. |
Approximately 40 permanent jobs will be needed to support
the long-term operation and maintenance of the facility. |
|
4. |
In
constructing the facility: |
|
- 644 pier foundations were drilled |
|
- 21,500 cubic yards of concrete were poured |
|
- 7,100 tons of steel will be used |
|
5. |
The
8.8-million-pound Unit 4 boiler is hung from the top of the
building. |
|
6. |
The
facility has three coal silos, each of which will hold
650 tons of coal. |
|
7. |
One of
the unit's environmental controls, a pulse jet fabric filter
baghouse, contains over 6,600 26-foot-long bags that
collect fine particulate from the flue gas. |
|
8. |
At 440
feet in height, the Unit 4 chimney is the second tallest
structure in Springfield. (The Unit 3 chimney is the
tallest; the Units 1 and 2 chimney is third tallest; and the
State Capitol is fourth.) Construction of the Unit 4 chimney
required only 28 days, 3 hours. |
|
Power Plants
Electric Generation
Electric Division
Last updated:
02/15/12
|