Photo montage of CWLP scenes with CWLP seal and link to CWLP home page. Click on words City Water, Light and Power to link to home page.

Dallman

The Dallman Power Station was built just to the southwest of the Lakeside Power Station in 1968 to answer the increasing electric demand of a growing city. It contains three coal-fired generating units. The Dallman 4 Power Station, which was built to the west of the original Dallman Station, was completed in 2009.

The first Dallman generator placed on line was Dallman 1, with a maximum capacity of 77 MW. It was followed by Dallman 2, an 83 MW unit in 1972. In 1978, the completion of Dallman 3, with a maximum capacity of 188 MW, more than doubled the power station's total generating capacity. Dallman 4 has a maximum capacity of 200 MW and provides the most cost-efficient energy of all of CWLP's generating units. (Read more about Dallman 4.) These four coal-fired units are intended to meet customer base load.

In 2010, the four Dallman generators used 1,397,170 tons of coal and 359,189 gallons of oil, all of which cost $56,845,955 to generate 2,551,510 MWH of electricity. The net fuel cost of these generators was $22.28 per MWH.

Environmental Controls
All four Dallman units are designed to burn coal with an approximate heat content of 10,500 Btu per pound. Particulate emissions from all four units are controlled by electrostatic precipitators. In addition, Dallman 4 utilizes a fabric filter bag house to aid in particulate emission control. 

In addition, the four units are equipped with  flue gas desulfurization systems (scrubbers) to control sulfur dioxide (SO2) emissions. The use of scrubbing technology, which uses limestone to trap SO2 in the flue gas before it can be emitted into the atmosphere, allows CWLP to meet and exceed federal Clean Air Act requirements while continuing to use high-sulfur Illinois coal. The byproduct from this process, synthetic gypsum, can be used as a soil amendment and in cement making. The scrubber for Dallman 3 was installed in 1980 and underwent a $30 million upgrade that was completed in the spring of 2012. As part of this upgrade, more modern system controls and efficient equipment were installed to allow the unit to continue to comply with Clean Air Act regulations. A second scrubber, serving Dallman 1 and 2, was put into operation in June 2001 in response to requirements of the 1990 Clean Air Act Amendments. Dallman 4's scrubber was built when the plant was constructed.

Each unit is also equipped with selective catalytic reduction (SCR) systems, which operate year-round to reduce nitrogen oxides (NOX) emissions to levels allowed by both state and federal clean air requirements.  The SCRs for the first three Dallman units, which cost a total of $76 million to install, were placed on line in May 2003.

In addition to the environmental control equipment described above, Dallman 4, one of the cleanest coal-fired generating units in the nation, is equipped with a powdered activated carbon injection system for mercury removal; and a state-of-the-art cooling tower that eliminates the need to send high-temperature condenser cooling water back into Lake Springfield. The other three Dallman Power Station units use once-through condenser cooling water systems with water being obtained from Lake Springfield and discharged back into the lake.

 

Last updated: 11/17/11