Photo of CWLP Electric Lines
Search CWLP web site.
CWLP home page.
CWLP web site table of contents.
Management team bios; Organizational chart; Contact information; Community outreach programs; Employment opportunities.
Power generation; Transmission & distribution; Tree trimming/line clearance.
Water purification; Drinking water quality; Water distribution system; Outside-the-city water customers; Water conservation; Water rates; Sewer fees.
Lake water quality, including e.coli monitoring results; Lake water levels; Water sports; Lake parks and reservation information; Lake real estate/property leases.
How to sign up for, transfer or terminate service; Updating your account records; Reading meters; Senior Citizen Discount Rate; Bill payment options; Understanding your bill; Electric, water and sewer rates.
Energy efficiency information; Energy Rebates (heat pumps, water heaters, insulation); Energy efficiency FAQs; Energy audits and technical assistance; Water conservation.
Special services for our business customers; Economic Development Rider; Business Energy Update.
Current news and information about CWLP activities.
Link to City of Springfield web site.
Contact information for comments or questions concerning CWLP web site.

 

The CWLP electric system's transmission network consists of lines and associated substations operating at voltages of 138 kV, 69 kV, and 34.5 kV.

             Page Divider Bar Graphic

The 138 kV portion of the transmission network currently includes approximately 63 circuit miles of overhead lines forming a complete loop around the system's service area. The purpose of the 138 kV network is to provide:

  • generator outlet capacity for CWLP's Dallman 3 unit and the main peaking turbine,
  • bulk power supply to the lower voltage portion of the transmission network,
  • a direct supply to six distribution substation transformers, and
  • interconnections with other utilities.

The 138 kV transmission lines presently serve nine of the system's substations or switching stations, plus the village of Chatham, Illinois.

A portion of the 69 kV transmission network was originally installed in 1956, and now consists of approximately 65 circuit miles of overhead lines serving 23 distribution substations. There are five 80,000 KVA transformers connecting the 138 kV system to the 69 kV system.

CWLP has five ties to the electrical transmission grid, one at 345 kV, three at 138 kV, and one at 69 kV.

The system's distribution network consists of approximately 555 circuit miles of overhead 12.47 kV and approximately 440 circuit miles of underground 12.47 kV facilities.

 