|
CWLP is in the process of constructing a new pulverized coal power plant that, when
completed in 2010, will be one of the cleanest coal-fired generating units
in the nation.

The new 200-MW unit, employing a Foster Wheeler pulverized coal boiler, will replace 76-MW of old coal-fired technology—the
utility's two Lakeside
turbine generators. Lakeside Units #6 and #7, CWLP's oldest
still-operating turbine generators, were placed into service in 1961 and
1965, respectively. They will be retired after the new plant becomes
operational.
The new generating station is expected to cost
approximately 20% less to operate per megawatt-hour than the most efficient
of the three existing
Dallman units.
The new plant will employ a number of environmental control
technologies, including low NOx burners for the boiler; a selective
catalytic reduction (SCR) system for additional NOx removal; powder
activated carbon injection for mercury removal; a fabric filter baghouse to
remove fine particulate; a wet flue gas desulfurization unit (scrubber) for
the removal of SO2; and a wet electrostatic precipitator to
remove acid mist and ultra-fine particulate from the flue gas. This equipment will assist CWLP in
its goal of becoming one of the most environmentally friendly primarily
coal-fired electric utilities in the nation.
The pollution control measures, as well as several other program
enhancements being planned by the utility, will enable CWLP to cut greenhouse
gas emissions sufficiently to meet the goals of reducing CO2
emissions to below 1990 levels and
complying with the State of Illinois' proposal to reduce mercury emissions by
90% by 2009. As part of its commitment to protect the environment, CWLP
will make pollution control improvements to the existing Dallman units;
increase its investment in consumer
energy efficiency programs; and purchase up to 120 MW of wind power each
year.
Air emission controls aren't the only way the new power plant will
complement the utility's efforts to protect and preserve the environment. By
utilizing state-of-the-art cooling towers, CWLP will be able to avoid
discharging high-temperature water from the plant into Lake Springfield.
During its estimated 42-month construction phase, the new plant is
expected to employ as many as 700 workers representing nearly a dozen local
labor unions.
KBV Springfield Power
Partners is serving as general contractor for the construction project. The
plant was designed by Black & Veatch.
|
Unit 4 Fun
Facts |
|
1. |
The
unit will burn 700,000 tons (1.4 billion pounds) of
Illinois coal each year. |
|
2. |
The
demand for coal will support 80 new mining jobs in Illinois. |
|
3. |
Approximately 40 permanent jobs will be needed to support
the long-term operation and maintenance of the facility. |
|
4. |
In
constructing the facility: |
|
- 644 pier foundations were drilled |
|
- 21,500 cubic yards of concrete were poured |
|
- 7,100 tons of steel will be used |
|
5. |
The
8.8-million-pound Unit 4 boiler is hung from the top of the
building. |
|
6. |
The
facility will have three coal silos, each of which will hold
650 tons of coal. |
|
7. |
One of
the unit's environmental controls, a pulse jet fabric filter
baghouse, will contain over 6,600 26-foot-long bags that
will collect fine particulate from the flue gas. |
|
8. |
At 440
feet in height, the Unit 4 chimney is the second tallest
structure in Springfield. (The Unit 3 chimney is the
tallest; the Units 1 and 2 chimney is third tallest; and the
State Capitol is fourth.) Construction of the Unit 4 chimney
required only 28 days, 3 hours. |
Unit
4 Construction Photo Gallery

This photo, taken in August 2006, shows the
land clearing and other
pre-construction work for the new plant that began several months earlier. The cleared area in the foreground of this photo indicates the new
plant site. The existing Dallman Power Station facilities are located just
right of photo-center. Part of the dark-brick Lakeside Power
Station, which will be retired when the new plant becomes operational, can be
seen at the far left. (Photo by Terry Farmer)

The construction site as it appeared on
January 12, 2007. (Photo by Terry Farmer)

A 280-foot crane towers over the Unit 4
construction site. This photo was taken in early January 2007 from the
Dallman 3 stack, looking west.

On February 22, 2007, workers poured nearly
1,200 yards of concrete, requiring approximately 133 truck deliveries. This
project, which created the boiler footings for the new plant, was the first
of several foundation installations that will be required during the
construction period.

In this aerial photo, taken March 1, 2007, the rectangular grey cement area
in the center of the construction site, just right of the crane support leg,
is the boiler footing that was poured on February 22. The rectangular area
to the left of the crane leg is another section of the boiler foundation,
which is expected to be poured on March 22. At the far right center of the
photo, the dark grey circular area surrounded by a reddish-colored exterior
is the foundation for the plant stack. (Photo by Terry Farmer)

This aerial photo was taken April 25, 2007,
looking north. In the foreground, work is just beginning on construction of
the Unit 4 stack. The white concrete area north of the stack is the
foundation mat for the air quality control system (AQCS), while north of that
are the five sections of the boiler foundation. Concrete for boiler
foundation sections two and four had yet to be poured when this photo was
taken. The tall black structure rising from the northern-most section
(section one) of the boiler footing is one of the four side forms for large
concrete columns that will support the turbine and generator. (Photo by Terry Farmer)
Watch Her Grow!
Construction of the Unit 4 stack (below) is taking place at lightning speed.
With crews working around the clock, the tower is now growing in height by
an average of 17 inches an hour. These photos, taken less than 24-hours
apart (on May 6 and 7), show how quickly the growth is occurring. On
May 7, the stack was 165 feet tall; on May 12, it was 257
feet tall; by 6 a.m. on May 15, it stood at 320 feet; and by 9 a.m. the
following day, it was 330 feet high. When completed, the stack will be 440 feet tall, with a 38 foot
diameter. Altogether, the outer "skin" will require 1,800 cubic yards of
concrete and 270,000 pounds of reinforcing steel. The interior of the
chimney will include 84,000 pounds of structural steel, approximately 450
linear feet of 15-foot fiberglass reinforced pipe, 6 grated platforms, one
elevator and a 450 foot safety ladder.
 |
 |

On May 15, the final part (section two) of
the Unit 4 boiler footing was poured. Note the green hue of the freshly
poured concrete.

Erection of the structural steel skeleton of
the main plant building, which will house the boiler and turbine, was well
underway when this photo was taken from the Unit 4 stack on July 24, 2007.
The large open area in the center of the building is where the boiler will
be located, while the upper-most section of the building will house the
turbine. Just north of the structure, you can see the plant's steam
condenser, which will eventually be lifted into its permanent place inside
the building.

This July 24, 2007, photo shows the frame of
the fabric filter baghouse, located just south of the main plant building.
The dark orange objects at photo-left are the baghouse walls, which are
waiting to be attached to the steel frame. The baghouse, one of the plant's
state-of-the-art environmental control technologies, will remove fine
particulates from the flue gas. The circular object at photo-right is the
foundation of the absorber slurry holding tank for the Unit 4 SO2
scrubber, which is yet to be built.
From the first day of construction through July
25, 2007, KBV (the general construction contractor) has installed
approximately 1300 tons of steel, 926 tons of rebar, and 9700 yards of
concrete.
On
August 23, 2007, the Unit 4 generator arrived at the plant site. The
generator weighs approximately a half-million pounds (250 tons) and is 28
feet long, 16 feet wide, and 14 feet high, making it the largest piece of
equipment brought on site for the new 200 MW facility. Transporting the
generator to the plant required a 320-wheel rig that also weighed about 250
tons.

These photos, taken in February 2008, show how far construction
has
progressed. In the far left corner of the building in the photo
above and
far right corner of the photo below, you can see that
sheet metal siding has
begun to be applied to the steel framework.
(Photo by Terry Farmer)

The following eight photos were also taken in February 2008:
(1)
The lower red pipe is the primary duct used to heat coal mills and transport
pulverized coal to the coal burners. It has a diameter of more than 8 feet.
The upper red duct is the overfire air duct that provides additional
combustion air to the boiler to ensure complete coal combustion. It has a
diameter of 7.5 feet and is located approximately 81 feet (about 8 stories)
above ground level.

(2) At the top center of this
photo, you can see the end of the overfire air duct pic- tured in Photo
#1 above. The red equipment pictured in the left half of the photo are 5
of the 9 coal burners that will ultimately be in-stalled. The gray pipes at
bottom left are coal conduits that will carry coal to the burners. The red
pipe running vertically on the right side of the photo is called a "down
corner." It will circulate water from the bottom to the top of the boiler as
water is heated and rises.
(3)

The red piece of equipment at the top of the
photo is the steam drum. It will separate water from steam in order to
prepare it for use in the steam turbine. The steam drum is located 164 feet
(about 16 stories) above ground level.
(4)

This photo depicts two important components
of Unit 4's environmental control system. The brownish-orange structure is
the pulse jet fabric filter. Over 6,600 filter bags enclosed inside this
structure will remove dust and mercury from the boiler flue gas before the
"smoke" is released into the air. Next, the flue gas will pass through the
SO2 scrubber/ absorber, the milk can-shaped structure pictured to the right
of the pulse jet fabric filter. (The upper portion of the scrubber/absorber
is pictured below in Photo #5.) The purpose of the scrubber/absorber
is to remove sulfur dioxide from the flue gas. To the far right of the
photo, you can see a portion of the Unit 4 smoke stack.
(5)

The top section of the SO2 scrubber/absorber
will eventually be lifted into position atop the milk can shaped structure
pictured in Photo #4 above. Once completed, the scrubber will be
approximately 120 feet tall.
(6)

The cylindrical portion of the limestone
ball mill holds steel balls that will crush rock limestone to a powder
consistency for use in the SO2 scrubber/absorber. The limestone powder can
then be mixed with water, forming a "slurry" that will be sprayed through
the flue gas stream to remove sulfur dioxide.
(7)
These four tanks will hold various liquids required in the air quality
control process. From left to right, the tanks are: (a) limestone slurry
storage tank, which is 32 feet in diameter and 34 feet tall and will hold
150,000 gallons; (b) reclaim water tank, which is 33 feet in diameter and 35
feet tall and will hold 171,000 gallons; (c) demineralizer water tank, which
is 26 feet in diameter and 32 feet tall and will hold 127,000 gallons; and
(d) slurry holding tank, which is 50 feet in diameter and 52 feet tall and
will hold 600,000 gallons.
(8)
The electrostatic precipitator pictured here is the last environmental
device through which Unit 4 flue gas will pass before entering the stack for
release into the atmo-sphere. The precipitator will collect acid mist and
fine particulate that are not captured by the pulse jet fabric filter or the
scrubber. Once in position between the top of the scrubber and the stack
inlet, this 24 foot by 27 foot device will be located about 140 feet above
ground level.
The following five photos were taken July 31, 2008:
(1)
Workers weld together sections of the boron mitigation effluent tank.
The rectangular structure to the right is the clarifier building for the
boron mitigation project.
(2)
A crane lifts rebar to the top of the fly
ash silo. In the back-ground is the steel framework of the boiler building.
(3)

Work progresses on the installation of the
Unit 4 control room.
(4)

When Unit 4 is completed, more than 1.7
million feet of electrical wire will run throughout the plant.
(5)

Although the steel siding had begun to be
applied to portions of the plant, the structural steel frameworks of
significant sections, including the boiler and air quality control buildings
remained bare on July 31, 2008.
The two aerial photos below show the progress made in
applying exterior finishes to the plant between September 1 (top) and
November 5, 2008 (bottom). (Photos by Terry Farmer)


Last updated:
12/08/08
Top
Electric Division
Wind Power
Generation
Electric T & D Fiber
Optics Tree
Trimming Security
Lighting
Electric
Rates
CWLP
Home Search
This Site
CWLP Contact Info
City of Springfield Home
|